So I just received the QB fuselage for my RV-14A via Partain. Very pleased with the shipping process.
Going thru the plans to make sure everything was completed when I discovered something interesting. On page 26-10, step 7 it says to cut out a rectangular hole for the main gear (tri-gear) and debur the edges before riveting the bottom skins together.
Problem is the hole was not cut out and the skins are riveted together. Not sure how to proceed. Will call Van's Monday am, but wondering if anyone else has dealt with this on the QB fuselage?