Page 10-10 says to "Flute the bottom flanges of the bulkhead as required to fit the F-01479 Aft Bottom Skin". There are enormous gaps between the bulkheads and the F-01479 Aft Bottom Skin but I can't seem to close them. You can see from the photos that I tried fluting the outer flange tabs but they did not get any closer.
Also, on Page 10-16, it says to "Dimple the pilot hole in the F-01479 Aft Bottom Skin as shown in Figure 1", then to "Use a rivet to fill the the pilot hole in the F-01479 Aft Bottom Skin as shown in Figure 1". What is the purpose of this?
Also, on Page 10-16, it says to "Dimple the pilot hole in the F-01479 Aft Bottom Skin as shown in Figure 1", then to "Use a rivet to fill the the pilot hole in the F-01479 Aft Bottom Skin as shown in Figure 1". What is the purpose of this?