I think the builder of my plane missed the note at the top of 28-07.
Page OP 62-02 shows the install of five nutplates on each side of the cover. These nutplates hold on the tunnel cover underneath the belly.
While investigating some streaky fluid underneath I set out to remove the tunnel cover and had difficulty removing some of the screws (had to pull really hard to get them to back out).
Turns out the 10 nutplates of 62-02 were never installed and instead ClickBond nutplates were used. Unfortunately in removing the tunnel cover screws the glue on most of the ClickBond plates broke seal and they ended up loose on the floor.
I'd appreciate any suggestion for what to use going forward for a more secure nutplate option.
On each side one location is under the pedals and another under the seat carry-thru. I've never riveted before and it looks like those locations would be a high difficulty. Additionally all the countersunk blind rivets I find seem to be 120°, not 100.
Page OP 62-02 shows the install of five nutplates on each side of the cover. These nutplates hold on the tunnel cover underneath the belly.
While investigating some streaky fluid underneath I set out to remove the tunnel cover and had difficulty removing some of the screws (had to pull really hard to get them to back out).
Turns out the 10 nutplates of 62-02 were never installed and instead ClickBond nutplates were used. Unfortunately in removing the tunnel cover screws the glue on most of the ClickBond plates broke seal and they ended up loose on the floor.
I'd appreciate any suggestion for what to use going forward for a more secure nutplate option.
On each side one location is under the pedals and another under the seat carry-thru. I've never riveted before and it looks like those locations would be a high difficulty. Additionally all the countersunk blind rivets I find seem to be 120°, not 100.