MPS Vibration Analysis Part 2 of 2
TEST CELL SETUP
The engine package, with its attachment frame, was bolted to a test stand consisting of the cabin structure of a Glastar kit plane, complete with firewall and a simplified instrument panel. Instruments included a tachometer, manifold pressure, engine oil temp, engine coolant temp, gear box temp, and exhaust gas temperatures from each cylinder. As seen in Figure 2 , controls included the ignition and throttle.
The cabin structure was bolted securely to a small trailer, allowing extended engine testing to take place on the far side of Arlington, WA airport, in an area designated by the airport authority for this purpose.
DATA COLLECTION AND SOFTWARE
The accelerometer used was the same as the one used by Steve Boese, a Freescale Semiconductor, Inc. evaluation kit, part number KIT3109MMA7260QE, with a mounting fabricated by our machine shop. The accelerometer has three axes, and a selectable range, from +/-1.5g to +/- 6g maximum.
We did not use a sensor on the propeller, since the propeller turns more slowly than the engine, due to the gear box, and we were primarily interested in engine-coupled vibrations. We did however use a tach signal from the ignition controller when required.
Data were collected from the accelerometer using a National Instruments USB-6009 Data Aquisition device (
http://www.machinevisiononline.org/buyers_guide/newproducts/details.cfm?id=770). We also used the National Instruments Signal View software that came with the device, on a Lenovo ThinkPad T61p, to process the data. Signal View is sophisticated enough to provide accelerometer voltage vs. frequency graphs out of the box, but not quite customizable enough to imbed calibration data for the accelerometer, and provide g level readings directly. Working backward from the maximum vibration levels permitted by
http://www.azimadli.com/images/severitychart.jpg, and the calibration data for the accelerometer, we calculated max voltage level at each frequency to remain within the acceptable and tolerable ranges for reciprocating engines.
RUNNING THE TEST
The engine was started on the test stand, and run at medium idle until temperatures and pressures were within the operating range. We had decided to test for vibration levels every 200 RPM from 3200 RPM to 5400 RPM. Throttle and prop pitch were adjusted for a typical engine output at each RPM, and a ten second sample of the vibration level recorded from the accelerometer. Between readings the engine RPM was returned to idle. Excluding warm-up, sampling and recording the data required approximately an hour run time.
PROCESSED DATA
Critical vibration frequencies are usually the first and second order, or 1X and 2X the engine RPM. Levels for these were read from the accelerometer data, along with the highest peak that was NOT a first or second order vibration. The data from every sample are shown in Table 1. Figures 3 demonstrates that the first and second order vibration levels are well below the maximum tolerable level. Figures 4 through 7 graphically displays the test run data for rpms of 3200, 4000, 4800, and 5400 respectively.
Figure 3 ? Vibration Tolerance Level Results
PSRU INSPECTIONS
In addition to the vibration analysis conducted on the MX1 PSRU, we also conducted a detailed examination of the PSRU during a complete tear-down following 75 hours of ground testing (See Figure 8 and Figure 9) as well as a visual inspection through a bore scope after approximately 120 hours. Both of these inspections revealed no wear beyond a normal break-in polish on either the pinion or driven gears. Bearings were still within nominal limits at 75 hours, and the torsional coupling components were in original condition.
CONCLUSIONS
We are pleased that the test results demonstrated vibration levels of the final MX1 system design were at acceptable levels, with only two minor excursions into the lower levels of the tolerable zone. The PSRU longevity continues to be evaluated, however initial inspections appear to corroborate that the design specifications for a 1500 hour TBO have been met and/or exceeded. As we continue to accrue actual flight hours on the first production PSRU now installed on N787MX, we continue to evaluate the system for evidence of gear wear. The total number of hours is nearly 350 (140 ground test and 190 flight test). We expect to do a complete tear-down inspection prior to AirVenture 2009 when the system should have approximately 400 hours logged.
We would like to acknowledge Mr. Steve Boese, his friend Doug Dempsey, and DLI Engineering for their willingness to share their knowledge and experience with the readers of Contact! Magazine. Our sincere appreciation also to the engineering staff at Lord Corporation and Mr. Hugh Evans for sharing their expertise.