I am at 10-16 Step 1 which says to csk all skin holes in the longeron (except for fairing screw holes), but I can't csk forward-most skin hole in the longeron because that 3/32 hole is not #40 match drilled yet.
I didn't match drill that hole yet because 10-12 Step 9 says to not drill any holes associated with F-1006 bulkhead, and the forward-most hole in the longeron lies over F-1006.
Seems that I should now drill the forward-most longeron hole to #40 and csk, but want to make sure this is correct so it doesn't cause an issue later at tailcone attach.
Appreciate any guidance -
Russell
I didn't match drill that hole yet because 10-12 Step 9 says to not drill any holes associated with F-1006 bulkhead, and the forward-most hole in the longeron lies over F-1006.
Seems that I should now drill the forward-most longeron hole to #40 and csk, but want to make sure this is correct so it doesn't cause an issue later at tailcone attach.