I have just finished using Sika Flex to bond the tip up canopy and back glass and it is cured. My question is what should come next? The plans say engine mount drilled to firewall is next. However, I do not have fuel pump, break lines, or rudder pedals installed yet. Also most firewall holes are not drilled. Side skins are still clecoed to the firewall. Should all of this be done before the engine mount is drilled to the firewall?
Trying not to get ahead of myself on this.