I'm just finishing my RV-7 rudder. I'm wondering if there are certain parts on the empenage and other parts of the airframe, that ought to wait to be installed (like the fiberglass tips), even if the instructions say to do it now?
When I built my Sonex the bottom fuselage skin went on the night before the DAR inspection. With the bottom skin off, it was super simple to work on anything in the cockpit, including the avionics. The Sonex instructions had me installing the bottom skin a good year before my inspection.
Are there things like that on the -7 that should wait, pending avionics, lights, etc., or that just make working on the project easier?
Thanks,
When I built my Sonex the bottom fuselage skin went on the night before the DAR inspection. With the bottom skin off, it was super simple to work on anything in the cockpit, including the avionics. The Sonex instructions had me installing the bottom skin a good year before my inspection.
Are there things like that on the -7 that should wait, pending avionics, lights, etc., or that just make working on the project easier?
Thanks,