tonyjohnson
Well Known Member
Has anyone installed an AV30E themselves, or have a lead on a reasonably priced avionics shop in the Tampa Bay area?
I have read online that the install time of the AV30 is much less than that of a G5, ranging as little as 2 hours with an average of 4 to 6 hours.
I spoke with an avionics shop today that quoted 10 hours to install it as an AI, and 20 hrs more to install it as a DG. They explained that the extra hours was because of the magnetometer (which the AV30 actually does not even have).
They would not be able to do the work until July.
I have read online that the install time of the AV30 is much less than that of a G5, ranging as little as 2 hours with an average of 4 to 6 hours.
I spoke with an avionics shop today that quoted 10 hours to install it as an AI, and 20 hrs more to install it as a DG. They explained that the extra hours was because of the magnetometer (which the AV30 actually does not even have).
They would not be able to do the work until July.