Van's indicates the lead times on quick build kits are about 2-4 months. Counting current rate of progress I estimate I should be done with the empennage kit in about 2 months, maybe a bit longer.
We have decided to order both QB fuselage and QB wings. Since we have a limited storage space, we won't be able to store completed empennage and wing kit while working on the fuselage (or vice versa).
Since I read here that QB wings comes almost completed, we thought about ordering QB fuse and postponing wing order until later. Is it a good idea?