Howdy! I ordered the empennage kit on 9/1 and the QB wing kit on 9/2. Should I go ahead and get the SB Fuselage kit on order now?
Here's my thinking. It looks like lead times just went up again. I think it will take 4-5 months to finish the empennage, but I don't expect that kit until the beginning of the year (it was 4 month lead time when I ordered it, now shows 6 months).
With the SB Fuselage kit now at 9 months lead time, and the "QB" wing kit at ~ 18months (or longer) I'm thinking I can use the time and not gap out by getting a SB Fuselage kit ordered now.
My thinking is I can use the time to work a SB Fuselage kit while the wings are the "critical path". Ideally I'd want to prevent months of gap and having to re-learn some skills.
Am I on the right track?
Here's my thinking. It looks like lead times just went up again. I think it will take 4-5 months to finish the empennage, but I don't expect that kit until the beginning of the year (it was 4 month lead time when I ordered it, now shows 6 months).
With the SB Fuselage kit now at 9 months lead time, and the "QB" wing kit at ~ 18months (or longer) I'm thinking I can use the time and not gap out by getting a SB Fuselage kit ordered now.
My thinking is I can use the time to work a SB Fuselage kit while the wings are the "critical path". Ideally I'd want to prevent months of gap and having to re-learn some skills.
Am I on the right track?