wirejock
Well Known Member
This is for my 7a slider
I'm reading ahead and missing something.
The manual talks about drilling the four bottom holes in the Vertical Stabilizer rear spar #30. I looked at DWG 27A. There is no dimensions to locate these four holes.
They correspond to four holes in the F-712E tie down bar but the bar is not yet installed and it is on the forward side of the bulkhead.
The manual mentions prepping the tie down bar by drilling the four holes that attach it to the F-712 bulkhead.
So how do you locate the other four holes common to the tie down, bulkhead and vertical stabilizer rear spar?
If they are drilled in the tie down, then how do you match drill in an area almost inaccessible except for the two access holes?
If they get drilled from the aft side, where are the dimensions to locate the holes?
I must be missing something and probably will fell stupid when it's pointed out but better to know now.
I'm reading ahead and missing something.
The manual talks about drilling the four bottom holes in the Vertical Stabilizer rear spar #30. I looked at DWG 27A. There is no dimensions to locate these four holes.
They correspond to four holes in the F-712E tie down bar but the bar is not yet installed and it is on the forward side of the bulkhead.
The manual mentions prepping the tie down bar by drilling the four holes that attach it to the F-712 bulkhead.
So how do you locate the other four holes common to the tie down, bulkhead and vertical stabilizer rear spar?
If they are drilled in the tie down, then how do you match drill in an area almost inaccessible except for the two access holes?
If they get drilled from the aft side, where are the dimensions to locate the holes?
I must be missing something and probably will fell stupid when it's pointed out but better to know now.