How long did you allow fuel tanks to cure before testing?
The tanks will be done (finally) tomorrow. I don't want to compromise the seal by testing too soon. After the z-brackets are installed, my plan was to put wax paper on the spar and mount them for a few days to allow them to fit before the proseal fully hardens.
When they go on the spar tomorrow it will be 50 till I remove them in the shop. Up to this point they have been inside at 70.
I can move them to the heater control room after but it runs low 90s.
I know temperature, mixing rates, etc. apply. I figure a week after they are removed from the spar should be fine but prefer to hear from others.
The tanks will be done (finally) tomorrow. I don't want to compromise the seal by testing too soon. After the z-brackets are installed, my plan was to put wax paper on the spar and mount them for a few days to allow them to fit before the proseal fully hardens.
When they go on the spar tomorrow it will be 50 till I remove them in the shop. Up to this point they have been inside at 70.
I can move them to the heater control room after but it runs low 90s.
I know temperature, mixing rates, etc. apply. I figure a week after they are removed from the spar should be fine but prefer to hear from others.