Working on a qb 10 fuselage. Working out conduit runs from aft to foreward. All floor panels removed for cleanup and access. I've already set up the back of fuselage to tailcone and wing conduit runs.
Question 1.
Since the main spar only has a low center hole cutout within the tunnel area, do most builders run a wiring conduit up the center tunnel? Given future rudder cable and elevator pushrod placement, is there a "better" low position left, right or bottom center? If not, how are you running antenna and tail strobe lines to panel?
Question 2.
I'm gradually getting my head around the wiring for wings. For the wires, that come in off the wings and into side panels, are you then routing the various wires, antenna leads, etc. through the side panel rear access grommet(currently conduit) and then to instrument panel through the center tunnel conduit mentioned in question 1 above?
I'm not trying to work out connections, wire from panel to wing or wing to panel, etc., here but best way to pass through or over main spar area.
Thanks in advance,
Tom H.
qb fuselage rv-10
Question 1.
Since the main spar only has a low center hole cutout within the tunnel area, do most builders run a wiring conduit up the center tunnel? Given future rudder cable and elevator pushrod placement, is there a "better" low position left, right or bottom center? If not, how are you running antenna and tail strobe lines to panel?
Question 2.
I'm gradually getting my head around the wiring for wings. For the wires, that come in off the wings and into side panels, are you then routing the various wires, antenna leads, etc. through the side panel rear access grommet(currently conduit) and then to instrument panel through the center tunnel conduit mentioned in question 1 above?
I'm not trying to work out connections, wire from panel to wing or wing to panel, etc., here but best way to pass through or over main spar area.
Thanks in advance,
Tom H.