OK, I've been over the plans a few times, and I'm sure there are some big steps missing before "Rolling over the canoe" on page 8-10.
The steps I don't see but i'm pretty sure i should do before rolling the canoe:
1 - drilling the firewall to the forward edge of the F-972 forward bottom skin
2 - drilling/installing those outboard seat ribs to the side skins
3 - riveting the F-972 forward bottom skin to the fuselage itself... the plans say to rivet the -970 skins on but don't actually tell you to rivet the F-972.
4 - Riveting the firewall to the fuse (there are two rows of rivets through the bottom skin and firewall... do i leave one or both of these open for now, or rivet them? not sure if the Cowel also gets riveted through this at the bottom.)
5- other miscellaneous drilling / riveting
I jut want to be sure that all the above tasks should in fact be done BEFORE rolling over the canoe.
The steps I don't see but i'm pretty sure i should do before rolling the canoe:
1 - drilling the firewall to the forward edge of the F-972 forward bottom skin
2 - drilling/installing those outboard seat ribs to the side skins
3 - riveting the F-972 forward bottom skin to the fuselage itself... the plans say to rivet the -970 skins on but don't actually tell you to rivet the F-972.
4 - Riveting the firewall to the fuse (there are two rows of rivets through the bottom skin and firewall... do i leave one or both of these open for now, or rivet them? not sure if the Cowel also gets riveted through this at the bottom.)
5- other miscellaneous drilling / riveting
I jut want to be sure that all the above tasks should in fact be done BEFORE rolling over the canoe.