I am ready to order the empennage but given the lead time of 12 weeks for the other kits I am wondering if I should order the fuselage at the same time. I plan to "invest" 24 hours per week but as a first time builder I expect lots of overhead time at the beginning (I built a shop for this project and it has to be set-up and organized first). Bottom line: I have no idea on the number of hours needed to finish the empennage. If I order both kits at the same time, I would have 240 hours of work before the fuselage comes in. Is this about right?