Hi builders,
I hit a snag installing the HS spar doubler. It is normally incorporated into the kits now, but I have an older kit and it was recommended I incorporate it during this stage of the build to prevent going back later.
As you can see above, there are 2 rows of rivets in the doubler without clecos. The one on the right is for the new rib attach point. However, the row on the left would interfere with the rib as pictured below:
Any thoughts? I was thinking about countersinking the rivet row on the left so that it wouldn't interfere, even though the plans specify universal head.
I know this seems like a simple question, just wanted to get the collective wisdom of VAF! Thanks in advance.
I hit a snag installing the HS spar doubler. It is normally incorporated into the kits now, but I have an older kit and it was recommended I incorporate it during this stage of the build to prevent going back later.
As you can see above, there are 2 rows of rivets in the doubler without clecos. The one on the right is for the new rib attach point. However, the row on the left would interfere with the rib as pictured below:
Any thoughts? I was thinking about countersinking the rivet row on the left so that it wouldn't interfere, even though the plans specify universal head.
I know this seems like a simple question, just wanted to get the collective wisdom of VAF! Thanks in advance.