ColoradoSolar

Well Known Member
I am working on section 28 and getting close to riveting in the Forward Center Section Bulkhead Assembly and the rivet diagram show 7 double flush rivets (see attached picture) but I can't find in the plans where it tells me to countersink the upper side of the flange. Am I missing it or is this just one of those steps Vans left out of the plans? Don't really want to make a mistake on the center bulkhead as I am sure that would be an expensive mistake.
 

Attachments

  • Screen Shot 2022-08-24 at 9.34.53 AM.png
    Screen Shot 2022-08-24 at 9.34.53 AM.png
    498 KB · Views: 109
Don’t have the plans with me but the reason for the double flush is to provide clearance for the gear weldment. Don’t forget to do the other side too.