NOTAM: !FNL 08/009 FNL APRON LIMITED PARKING AVBL WEF 1308231346-1310112300
Is this going to adversely impact parking for LOE 2013?
Here is what we received. However this was before the rains. I would imagine this might get delayed somewhat:
"
Good Afternoon Everyone,
The GA Ramp Rehabilitation project will begin next Monday, August 19th. The project is broken down into three phases with the schedules of each phase as follows:
1. Phase I beginning August 19 thru September 24
2. Phase II beginning September 24 (or Phase I rehabilitation completion) thru October 7
3. Phase III beginning October 7 (or Phase II rehabilitation completion) thru October 18
Completion date of the total project is scheduled for October 18.
There will be closures of ramp and ramp access throughout the project, but the project has been phased so all hangar tenants and airport businesses will have access to the runway. During Phase I and Phase II Taxiways B and D will be the best route to/from hangars to/from Taxiway A. Taxiway C will be used by itinerant aircraft and will be directed to ramp parking by the jetCenter.
Aircraft leasing tie-downs from the jetCenter will be relocated to tie-downs on the very south section of the ramp during construction.
Tenants accessing the airport via Gate #2, please be cautious during the project as Front Range Helicopters will be operating on the ramp area, east side of the large jetCenter hangar.
NOTAMs will be issued throughout the project.
NOTE: As with all construction projects, these schedules are subject to change due to unforeseen issues that may arise, but I will keep everyone informed as the project proceeds.
Thank you,
"