Michael Burbidge
Well Known Member
![Screenshot 2024-01-16 at 5.48.04 PM.png Screenshot 2024-01-16 at 5.48.04 PM.png](https://vansairforce.net/data/attachments/32/32769-6b2a6f95b2d434a8464088920ad78231.jpg)
I wanted to confirm the rivets to be used in connecting the baggage ribs to the bulkhead. The diagram shows 8X LP4-3 with arrows pointing to three rivet holes. I assume that this means that an LP4-3 should be used in the bottom hole of all 8 baggage ribs (left and right side). Likewise the diagram shows 16X AN470AD4-4, with a single arrow pointing to one of the baggage rib holes. I assume this refers to the top two holes of each of the 8 baggage ribs (left and right side).
Is my understanding of the diagram correct?
Thanks, Michael-