Quote:
|
.....would like to go as far as possible before moving the project to the airport........
|
"
Go as far as possible".....my sentiments exactly. It makes good sense to do as much work as possible before moving the project to the airport. I made the mistake of moving my -6A to the airport well before it really needed to be moved and as a consequence, final assembly took several months.
You don't say which RV you are building. My most recent experience is building a standard kit RV-8 and here's what I did the second time around:
Before making the move, I completed virtually everything possible in my home garage. That work included everything firewall forward, all fiberglass components fitted and the instrument panel completed, all circuits tested. Virtually all electrical circuits in the wings were prewired and tested so when the wings were finally installed, it was just a question of plugging it all in at the wing root. Final assembly at the airport was greatly simplified and took less than 3 weeks of a 24 month build time.