Default Prosealing elevator skin stiffeners

I'm at the point of back riveting my stiffeners to the .016" elevator skins and I read of a lot of issues with cracks propagating from the last rivet hole at either end but most often the trailing edge end. I will be following all the usual recommendations; proper bend radius, glob of RTV. I plan on doing the proseal mod too but I'm wondering if those who have gone this route would recommend doing the entire length of the stiffener or just the ends, maybe an inch or so? Seems like it could be unnecessarily messy to do the whole length and add time/weight.
Reply With Quote
  #2  
Old 06-04-2015, 07:16 PM
wirejock's Avatar
wirejock wirejock is offline
 
Join Date: Oct 2005
Location: Estes Park, CO
Posts: 3,931
Default Proseal stiffeners

Quote:
Originally Posted by NorthernRV4 View Post
I'm at the point of back riveting my stiffeners to the .016" elevator skins and I read of a lot of issues with cracks propagating from the last rivet hole at either end but most often the trailing edge end. I will be following all the usual recommendations; proper bend radius, glob of RTV. I plan on doing the proseal mod too but I'm wondering if those who have gone this route would recommend doing the entire length of the stiffener or just the ends, maybe an inch or so? Seems like it could be unnecessarily messy to do the whole length and add time/weight.
I did mine. It's not flying yet so I can't comment on the long term or how much weight was added. I doubt it was much. It was not messy compared to fuel tanks!
__________________
Larry Larson
Estes Park, CO
http://wirejockrv7a.blogspot.com
wirejock at yahoo dot com
Donated 12/03/2019, plus a little extra.
RV-7A #73391, N511RV reserved (2,000+ hours)
HS SB, empennage, tanks, wings, fuse, working finishing kit
Disclaimer
I cannot be, nor will I be, held responsible if you try to do the same things I do and it does not work and/or causes you loss, injury, or even death in the process.
Reply With Quote
  #3  
Old 06-04-2015, 09:11 PM
David Paule David Paule is offline
 
Join Date: Dec 2009
Location: Boulder, CO
Posts: 4,428
Default

I did mine, too, full length. I'm doing that for all the .016 control surfaces in the slipstream.

Dave
RV-3B, (very) slow build, now on ailerons, out of the slipstream
Reply With Quote
  #4  
Old 06-05-2015, 06:32 PM
woodmanrog's Avatar
woodmanrog woodmanrog is offline
 
Join Date: May 2005
Location: Florida
Posts: 774
Default

Do it for the full length. You don't want gaps between the two surfaces.
Reply With Quote
  #5  
Old 06-05-2015, 11:32 PM
omrsramsay's Avatar
omrsramsay omrsramsay is offline
 
Join Date: Jul 2013
Location: Milwaukie, OR
Posts: 35
Default

When I worked at Columbia Helicopters, the policy for the sheet metal department to reduce cracking and working rivets, was to seal every riveted joint, and use solid rivets wherever possible. I believe Erickson had the same policy, except the reason for it was to prevent cracks, working fasteners, and the tail falling off and everyone dying.
__________________
John Kimmel
http://www.youtube.com/watch?v=ZOa7Xsc2P_M
Reply With Quote
  #6  
Old 06-06-2015, 01:03 AM
Ralph Inkster Ralph Inkster is offline
 
Join Date: Feb 2008
Location: Calgary, Alberta
Posts: 999
Default

I have never seen cracks along the length of the stiffeners, only at the end rivets. Flexing of the skins beyond the stiffeners is the problem.

What I do- shape the stiffeners with a small 90deg tab at the spar end, apply a small blob of proseal at the trailing edge to tie the 2 converging stiffeners together, also apply proseal blob to those little bent tabs to fglue the stiffeners to the spar. This takes care of all that nasty flexing. I've not had a crack show up on any surfaces built using this process.
__________________
Ralph
built a few RVs, rebuilt a few more, hot rodded some, & maintained/updated a bunch more
Reply With Quote
  #7  
Old 06-06-2015, 06:39 AM
NorthernRV4's Avatar
NorthernRV4 NorthernRV4 is offline
 
Join Date: Mar 2013
Location: Prince Edward Island, Canada
Posts: 138
Default

Thanks fellas! I will pro seal the entire length, if anything it's good practice for when I get to the tanks.

Ralph, I like the idea of a blob at each end, I hadn't considered the end where the stiffener meets the spar. A little tough when it comes time to close the ctrl surface, no? Having never used pro seal, when it cures where is it on the scale of hardness? JB Weld -> RTV silicone?
Reply With Quote
  #8  
Old 06-06-2015, 06:54 AM
Mel's Avatar
Mel Mel is offline
 
Join Date: Mar 2005
Location: Dallas area
Posts: 10,762
Default

If the trailing edge bends are properly done, there shouldn't be any problems. My -6 has been flying since early 1993 with .016" skins, no pro-seal, no RTV, and no cracks whatsoever.
__________________
Mel Asberry, DAR since the last century.
EAA Flight Advisor/Tech Counselor, Friend of the RV-1
Recipient of Tony Bingelis Award and Wright Brothers Master Pilot Award
USAF Vet, High School E-LSA Project Mentor.
RV-6 Flying since 1993 (sold)
<rvmel(at)icloud.com>
Reply With Quote
  #9  
Old 06-06-2015, 07:17 AM
wirejock's Avatar
wirejock wirejock is offline
 
Join Date: Oct 2005
Location: Estes Park, CO
Posts: 3,931
Default Proseal

Quote:
Originally Posted by NorthernRV4 View Post
Thanks fellas! I will pro seal the entire length, if anything it's good practice for when I get to the tanks.

Ralph, I like the idea of a blob at each end, I hadn't considered the end where the stiffener meets the spar. A little tough when it comes time to close the ctrl surface, no? Having never used pro seal, when it cures where is it on the scale of hardness? JB Weld -> RTV silicone?
It's a little harder than RTV.
I wouldn't op it on like tanks. A thin coat on both surfaces should suffice then a glob about the size of a piece of chewing gum at the intersection of each pair.
Buy the small size from Vans. It's enough to do the control surfaces.
__________________
Larry Larson
Estes Park, CO
http://wirejockrv7a.blogspot.com
wirejock at yahoo dot com
Donated 12/03/2019, plus a little extra.
RV-7A #73391, N511RV reserved (2,000+ hours)
HS SB, empennage, tanks, wings, fuse, working finishing kit
Disclaimer
I cannot be, nor will I be, held responsible if you try to do the same things I do and it does not work and/or causes you loss, injury, or even death in the process.
Reply With Quote
  #10  
Old 06-06-2015, 10:37 AM
Ralph Inkster Ralph Inkster is offline
 
Join Date: Feb 2008
Location: Calgary, Alberta
Posts: 999
Default

May be coincidence, not sure, but I see more cracking on planes with 360s & bigger more often than on 320 planes.
Proseal, or RTV fine to use. RTV definitely easier. The little flange I bend at the front end of the stiffeners is to have a surface the blob can hold to while sliding the spar in for riveting.
Note if gluing the whole stiffener- keep it light as these surfaces have to be balanced later.
__________________
Ralph
built a few RVs, rebuilt a few more, hot rodded some, & maintained/updated a bunch more
Reply With Quote
Reply



Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -6. The time now is 03:00 AM.


The VAFForums come to you courtesy Delta Romeo, LLC. By viewing and participating in them you agree to build your plane using standardized methods and practices and to fly it safely and in accordance with the laws governing the country you are located in.