Default Dynon 10" HDX install for RV-6a panel

I finally decided to go with the Dynon 10" HDX for my RV-6a panel.
I am getting 1 screen for now but will wire a second connector for expansion as funds are available.
I am getting -

2 axis AP servos w/install kits
AP panel
2 place intercom
knob panel
SV-GPS-250 GPS
UAVIONIX BUNDLE ECHO UAT / SKYFY-EXT ALL IN ONE ADS-B in/out
SV-ADAHRS-200
SV-EMS-220 engine monitor w/ lycoming L4C probe kit
DYNON EMS FUEL FLOW SENSOR
SV-Com-X25
1- Network Hub
1- wifi adapter
1- battery backup
FPS-PLUS WITH ELEVATOR TRIM


I am hoping to find someone that has mechanical drawings showing placement of components along with cable lengths that are needed to complete the install.
I'm looking forward to my new panel.
__________________
Rob W
1973 Cessna 177RG sold
1974 Cessna turbo normalized 177RG Sold
Vans RV-6a N543RV owner
Disabled Vet, but my paid dues are worth the minimal cost.
__________________
Rob W
1973 Cessna 177RG sold
1974 Cessna turbo normalized 177RG Sold

Vans RV-6a N543RV owner
Disabled Vet, but my paid dues are worth the minimal cost.
Reply With Quote
  #2  
Old 11-15-2020, 02:19 PM
PhatRV PhatRV is offline
 
Join Date: Mar 2018
Location: Buena Park, California
Posts: 420
Default

Each setup is different for each plane. The cable length is entirely from the placement of your avionic, the circuit breaker location, ground locations, etc... You should layout the avionics so they fit your panel. Once the avionics are mounted, the wiring can begin by routing each wire at a time, and leave some extra wire length for serviceability. Needless to say, its a tedious process.

Unfortunately, this isn't like the RV12 where the LSA rule dictates the fixed panel layout and the wiring loom can be purchased ahead of time
__________________
RV8 standard build: Empennage 99% completed
Wing -- Closed
Fuselage -- Canopy Done. Fiberglass 80%
Avionics Installation -- 90%
Firewall Forward -- Prep for cowl install
Electrical -- 90%

Donation paid through 2021
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -6. The time now is 09:28 AM.


The VAFForums come to you courtesy Delta Romeo, LLC. By viewing and participating in them you agree to build your plane using standardized methods and practices and to fly it safely and in accordance with the laws governing the country you are located in.