  #1  
Old 01-27-2021, 11:51 AM
Desert Rat Desert Rat is offline
 
Join Date: Aug 2018
Location: Wichita KS
Posts: 915
Default Finishing kit lead times :(

Just ordered my RV7 finishing kit and the estimated lead time for crating is now 6-7 months. The last time I looked it was quite a bit less than that. I want to say 16 weeks?

Shame on me for not thinking about what Covid might do to production schedules and ordering this 3 months ago!
__________________
Terry Shortt
AGI, CFI, CFII, MEI, A&P, Janitor
RV7 Empennage & Wing done
Fuselage in process
#72651
https://eaabuilderslog.org/?blprojec...t=all&listcat=
Reply With Quote
  #2  
Old 01-27-2021, 12:45 PM
fcordrey fcordrey is offline
 
Join Date: Jun 2014
Location: Aulander,NC
Posts: 29
Default

I know how you feel. When the lead times started getting longer I ordered my RV7 finishing kit. That was back in September and it was scheduled to be crated this week. They notified me last week it would be another 2-4 weeks before it'll be crated.

Oh well...good things come to those who wait!
__________________
Frank Cordrey #74600
Private SEL/SES
RV-7 Emp Done
Wings 80%
Fuselage started- canoe flipped
Finish kit inventoried
Reply With Quote
  #3  
Old 01-28-2021, 11:51 AM
lr172 lr172 is offline
 
Join Date: Oct 2013
Location: Schaumburg, IL
Posts: 7,277
Default

Quote:
Originally Posted by Desert Rat View Post
Just ordered my RV7 finishing kit and the estimated lead time for crating is now 6-7 months. The last time I looked it was quite a bit less than that. I want to say 16 weeks?

Shame on me for not thinking about what Covid might do to production schedules and ordering this 3 months ago!
Thats Crazy. I ordered mine 15 months ago and it was around 3 weeks.
__________________
N64LR - RV-6A / IO-320, Flying as of 8/2015
N11LR - RV-10, Flying as of 12/2019
Reply With Quote
  #4  
Old 01-28-2021, 11:58 AM
jacoby jacoby is offline
 
Join Date: Jul 2018
Location: WNC
Posts: 335
Default

Quote:
Originally Posted by lr172 View Post
Thats Crazy. I ordered mine 15 months ago and it was around 3 weeks.
I ordered my slow build -10 fuselage Monday and got a 7/19 crating date. Right at 6 months. It seems like Van's is just out of capacity to go faster.
Reply With Quote
  #5  
Old 01-29-2021, 08:51 AM
Paul 5r4 Paul 5r4 is offline
 
Join Date: Oct 2006
Location: Foley, Al
Posts: 691
Default

If it's just a matter of crating and shipping.... Would they let you come and pick it up. Sounds like this is affecting lots of people. Maybe a few folks ban together and rent a truck then go pick the stuff up. Another thought is to price out each item in the FF kit and price it elsewhere. Probably more expensive but lot less wait time.
__________________
Paul Gray
Foley, Alabama
N729PG..... 500+ hrs
RV 7A, Lycoming 0 320 D1A, Sensenich FP propeller
pilotforfun2001@yahoo.com
VAF supporter $$$
Reply With Quote
  #6  
Old 01-29-2021, 03:23 PM
Desert Rat Desert Rat is offline
 
Join Date: Aug 2018
Location: Wichita KS
Posts: 915
Default

I didn't ask specifically, but I'm assuming that it's not just a matter of crating & shipping. I imagine they are cranking out parts as fast as they can, but Covid has a ton of us home ordering stuff.

In my case, it's the finish kit, not the firewall fwd kit. gear legs, canopy, cowling, stuff like that.
__________________
Terry Shortt
AGI, CFI, CFII, MEI, A&P, Janitor
RV7 Empennage & Wing done
Fuselage in process
#72651
https://eaabuilderslog.org/?blprojec...t=all&listcat=
Reply With Quote
  #7  
Old 01-29-2021, 04:11 PM
D Weisgerber's Avatar
D Weisgerber D Weisgerber is online now
 
Join Date: Sep 2019
Location: Ionia Michigan
Posts: 353
Default

I believe Vans is having a hard time getting parts that they don't make in house. I got my finish kit about a month ago. Several parts were backordered including the tires. I just cancelled my tires and got a set from ACS. I'm still waiting for the axle nuts, axle mounting hardware and the canopy latch.
__________________
Dave Weisgerber
RV8 N848DW. Ser#83830 done.
James Cowl
DAR inspection on 7-23-2021
First flight on 7-25-2021
Phase 2 on 9-3-2021
Reply With Quote
  #8  
Old 01-29-2021, 07:54 PM
David Z David Z is offline
 
Join Date: Aug 2010
Location: Thunder Bay Ontario
Posts: 932
Default

Quote:
Originally Posted by Desert Rat View Post
... Covid has a ton of us home ordering stuff
That's certantly true. While I used to work 3-6 days per week, now I'm down to about 1 day of work per week. That's a lot more progress happening on the plane, which means ordering more stuff to keep up.
__________________
RV8
Empennage Passed Pre-close Inspection
Wings mostly done
Fuselage assembly, it's a riveting job!
83126
Dash 8 day job is financing the RV8
Donation till September 2022
Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

vB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Forum Jump


All times are GMT -6. The time now is 04:50 PM.


The VAFForums come to you courtesy Delta Romeo, LLC. By viewing and participating in them you agree to build your plane using standardized methods and practices and to fly it safely and in accordance with the laws governing the country you are located in.